Chinese Pilot Plant

Operating since December 2023, our 650 sqm Hunan facility has run the full concentrate-to-cathode process across multiple campaigns. It is the operating evidence behind the Australian Demonstration Plant.

Operating since December 2023

Continuous development with rapid innovation cycles, across multiple successful concentrate-to-cathode campaigns.

150+ batches above China industry standards

Sustained production performance benchmarked against Chinese industry standards across multiple campaigns.

De-risking the ADP

China-developed process know-how, now paired with Western engineering, safety and regulatory standards for deployment in Perth.

Multiple manganese chemistries

Flexible production across HPMSM, MFP and other advanced manganese battery chemicals, spanning both LMFP and LMR cathode pathways.

Circular by design

An ore-agnostic flowsheet with circular by-product recycling, targeting a zero-tailings system.

Energy-saving process

Our high-efficiency electric calcination kiln uses at least 70% less electricity, and our 5th generation crystallisation reactor 90% less energy than a conventional single-effect evaporator.

Proposed plant

Tier-1 economics and a low-cost pathway to production

Feasibility Study completed in May 2024 outlined a compelling opportunity to establish a near-term, cost-competitive, battery-grade manganese sulphate operation.

Key highlights included:

Low Capital Expenditure (CAPEX)US$83.5 million
Working CapitalUS$10.7 million
Plant CapacityProducing 50,000 tonnes per annum (t/a) of battery-grade MnSO₄ and 10,000 t/a of Mn₃O₄, or an equivalent of 72,500 t/a of MnSO₄
Sustainable ProcessFacility designed to be environmentally friendly, generating no wastewater and ensuring all residues are utilised by a cement plant
Operational EfficiencyProject OPEX very competitive with peers in China, profitable with today's pricing and does not depend on subsidies from joint venture partners or Government, underscoring the plants economic viability
~60% of Financing SecuredThrough indicative and non-binding agreements with key partners, including China Chemical and China Construction Bank
Permits and ApprovalsAll critical permits required to operate, including environmental, safety, and energy obtained in a timely manner. Preliminary design completed and approved by the Jinshi High-Tech Industrial Park Committee, covering roughly 80% of the requirements for the building permit. Building permit expected to be granted shortly after completion of the detailed engineering design.

Refer to ASX announcements 7/5/24, 14/5/24, 28/5/24, 10/9/24 and 24/9/24.

Funding structure

CAPEX of US$83.5M plus US$10.7M working capital, funded across equity and non-binding partner facilities.

  • Equity45%
  • China Construction Bank (CAPEX)41%
  • China Construction Bank (Working Capital)7%
  • China Chemical (CAPEX deferred payment)7%