FRB Investor Presentation to IMARC 2024
Released
Released
Announcement PDF
MANGANESE: THE KEY TO
POWERING TOMORROW’S BATTERIES
IMARC CONFERENCE
OCTOBER 2024
ASX:FRB
DISCLAIMER
CAUTIONARY STATEMENT – SULPHATE FEASIBILITY STUDY
This presentation contains summary information about Firebird Metals Limited (Firebird) (ABN 24 610 035
535) and is current as of 28 October 2024. The information in this presentation is of a general background and
does not purport to be complete. This presentation is not investment or financial product advice (nor tax,
accounting or legal advice) and is not intended to be used for the basis of making an investment decision.
The Feasibility Study referred to in this presentation is a Technical Feasibility of the establishment of the Battery Grade Manganese
Sulphate Project Stage 1 Processing Plant in China (the Plant). The Feasibility Study is based on the material assumptions contained in the
Feasibility Study document released to the ASX on 7 May 2024. These include assumptions about the availability of funding. While the
Company considers all of the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be
correct or that the range of outcomes indicated by the Feasibility Study will be achieved.
The information contained in this presentation has been prepared without taking into account the objectives,
financial situation or needs of individuals. Investors should obtain their own advice before making any
investment decision. Firebird has prepared this document based on information available to it at the time of
preparation. No representation or warranty, express or implied, is made as to the fairness, accuracy or
completeness of the information, opinions and conclusions contained in this presentation.
This presentation contains certain “forward-looking statements”. Forward looking statements can generally be
identified by the use of forward-looking words such as, “expect”, “should”, “could”, “may”, “predict”, “plan”,
“will”, “believe”, “forecast”, “estimate”, “target” and other similar expressions. Indications of, and guidance on,
future earnings and financial position and performance are also forward-looking statements. Forward- looking
statements, opinions and estimates provided in this presentation are based on assumptions and
contingencies which are subject to change without notice, as are statements about market and industry
trends, which are based on interpretations of current market conditions. Forward-looking statements
including projections, guidance on future earnings and estimates are provided as a general guide only and
should not be relied upon as an indication or guarantee of future performance
This presentation contains statements that are subject to risk factors associated with Firebird and the mining
exploration industry. It is believed that the expectations reflected in these statements are reasonable, but they
may be affected by a range of variables which could cause actual results or trends to differ materially. Firebird
disclaim any intent or obligation to publicly update any forward-looking statements, whether as a result of
new information, future events or results or otherwise. To the maximum extent permitted by law, Firebird,
their related bodies corporate (as that term is defined in the Corporations Act 2001 (Cth) and the officers,
directors, employees, advisers and agents of those entities do not accept any responsibility or liability
including, without limitation, any liability arising from fault or negligence on the part of any person, for any
loss arising from the use of the presentation or its contents or otherwise arising in connection with it.
JORC Compliance Statement
This announcement contains references to Exploration Results and Mineral Resource Estimates, which have
been reported in compliance with ASX Listing Rules 5.7 and 5.8 and extracted from previous ASX
announcements as referenced. The Company confirms that it is not aware of any new information or data
that materially affects the information included in the said announcements, and in the case of estimates of
Mineral Resources, that all material assumptions and technical parameters underpinning the estimates in the
relevant market announcements continue to apply and have not materially changed.
The Company confirms that the material assumptions and technical parameters underpinning the production
target disclosed in the Company's announcement dated 7 May 2024 continue to apply and have not materially
changed.
For full details refer to ASX announcements 10/3/22, 30/1/23, 23/3/23, 26/6/23, 30/8/23, 1/9/23,
18/10/23, 21/11/23, 13/12/23, 29/1/24, 13/3/24, 7/5/24, 14/5/24, 28/5/24, 5/6/24, 10/9/24, 12/9/24,
24/9/24, 2/10/24, 21/10/24 and 28/10/24
Oakover Resource: Indicated Resource of 105.8Mt at 10.1%; Inferred Resource of 70.9Mt at 9.6% for
global Resource of 176.7 Mt at 9.9% Mn
Hill 616 Resource: Inferred Resource of 57.5 Mt at 12.2% Mn
Notwithstanding the developments set out in this quarterly report, Investors should note that there is no certainty that the Company will
be able to raise the amount of funding to develop the Plant when needed. It is also possible that such funding may only be available on
terms that may be dilutive to or otherwise affect the value of Company’s existing shares.
It is also possible that the Company could pursue other ‘value realisation’ strategies such as a sale, partial sale or joint venture of the
Plant. If it does, this could materially reduce the Company’s proportionate ownership of the Plant. Given the uncertainties involved,
investors should not make any investment decisions based solely on the results of the Feasibility Study.
CAUTIONARY STATEMENT- DMS CONCENTRATE SCOPING STUDY
The Updated Scoping Study announced to the ASX on 30 August 2023 has been undertaken for the purpose of initial evaluation of a
potential development of the Oakover Manganese Project. The Scoping Study is a preliminary technical and economic study of the
potential viability of the Oakover Manganese Project as a manganese producer. The Scoping Study outcomes, production target and
forecast financial information referred to in this release are based on low accuracy level technical and economic assessments that are
insufficient to support estimation of Ore resources.
The Scoping Study has been completed to a level of accuracy of +/- 35% in line with a scoping level study accuracy. While each of the JORC
modifying factors was considered and applied, there is no certainty of eventual conversion to Ore Reserves or that the production target
itself will be realised. Further exploration and evaluation work and appropriate studies are required before the Company will be in a
position to estimate any Ore Reserves or to provide any assurance of an economic development case. Accordingly, given the uncertainties
involved, investors should not make any investment decisions based solely on the results of the Scoping Study. Given that the results of
the Scoping Study are subject to the qualifications above (including assumptions as to accuracy), any results reported in this release
should be considered as approximates and subject to variances having regard for the assumptions referred to in this release. The
Company has reasonable grounds for disclosing a Production Target, given that approximately 99% of the Life-of-Mine (LOM) Production
Target is in the Indicated Mineral Resource category, and 1% is in the Inferred Mineral Resource category. The production target stated in
this announcement is based on Firebird’s current expectations of future results or events and should not be relied upon by investors
when making investment decisions. Further evaluation work and studies are required to establish sufficient confidence that the
production target will be met. Firebird confirms that the financial viability of the Oakover Manganese Project is not dependent on the
inclusion of Inferred Resources in the Scoping Study.
The Company considers all the material assumptions in this Study to be based on reasonable grounds. These include assumptions about
the availability of funding. While Firebird considers all of the material assumptions to be based on reasonable grounds, there is no
certainty that they will prove to be correct or that the range of outcomes indicated by the Scoping Study will be achieved. To achieve the
range of potential outcomes indicated in the Scoping Study, funding of in the order of $123 million (excluding working capital and finance
costs) will likely be required. Investors should note that there is no certainty that Firebird will be able to raise that amount of funding
when needed. However, the Company has concluded it has a reasonable basis for providing the forward-looking statements included in
this announcement and believes that it has a "reasonable basis" to expect it will be able to fund the development of the Project. It is also
possible that such funding may only be available on terms that may be dilutive to or otherwise affect the value of Firebird’s existing
shares. It is also possible that Firebird could pursue other ‘value realisation’ strategies such as a sale, partial sale or joint venture of the
project. If it does, this could materially reduce Firebird’s proportionate ownership of the project. Given the uncertainties involved,
investors should not make any investment decisions based solely on the results of the Scoping Study.
The Mineral Resources underpinning the production target in the Scoping Study have been prepared by a competent person in
accordance with the requirements of the JORC Code (2012). For full details of the Mineral Resources estimate, please refer to Firebird’s
ASX release dated 23 March 2023. Firebird has confirmed that it is not aware of any new information or data that materially affects the
information included in that release. All material assumptions and technical parameters underpinning the estimates in that ASX release
2
continue to apply and have not materially changed.
MARKET OVERVIEW
THE SHIFT TOWARDS MANGANESE-RICH CATHODE MATERIALS
• Focus on Cathode Development: The performance of Li-ion batteries is largely driven by cathode materials. There are countless
chemical combinations, making cathode development a key focus area
• Market Shift to LFP: Nickel-based cathodes (Ternary) once dominated the market, but now Lithium Iron Phosphate (LFP) batteries
have taken over, representing more than 70% of the market share
• Why LFP? LFP is more affordable (1/3 the cost of nickel-based materials), safer with higher thermal stability and provides good range
capabilities with innovations like blade technology
• LFP Limitations and LMFP Emergence: LFP has reached its capacity limits. The next evolution, with the market starting to grow
quickly, is Lithium Manganese Iron Phosphate (LMFP), an upgraded and lower-cost version of LFP
• Advantages of LMFP: LMFP provides up to 20% higher energy density compared to LFP, offering performance on par with mid-level
nickel-based batteries, while being far more cost-effective on a wh/kg basis
• Soochow Securities forecast LMFP will replace 50% of LFP batteries by 2030
• Caitong Securities forecast blending LMFP with nickel-based batteries in China to reach 30% by 2030
• Critical Role of MnSO4 & Mn3O4: High purity Manganese Sulphate (MnSO4), Manganese Tetroxide (Mn3O4) and derivatives are
essential for producing Cathode Active Material
• Firebird well-positioned to efficiently grow into a near-term and low-cost MnSO4 and Mn3O4 producer and
become a key supplier to a rapidly growing market
Source: Company research
4
CRITICAL ROLE OF MANGANESE IN BATTERIES
Traditional
Uses
• Manganese has a long history of being a cathode
material for batteries in the form of Electrolytic
Manganese Dioxide (EMD)
Manganese content (100% Mn metal basis) in per battery in each vehicle above
Source: Benchmark Mineral Intelligence
Manganese
Lithium-ion
Batteries
• Mn is used in Li-ion batteries, including NCM, LMO
and LMFP – due to significant benefits of LMFP, the
use of this cathode mix is set for massive growth
• Size and growth of LMFP market is potentially
the largest in medium to long term (est. avg.
900kg of MnSO4 per 1 tonne of LMFP)
Indicative Metals Intensity By Battery Type
LFP
NCA
NCM 9½½
NCM 811
Mn
NCM 712
Na-ion
Batteries
• Na-ion batteries inherently have lower density
• Some sodium batteries contain around 30% Mn
Research and advocates for manganese rich batteries is on the
rise, due to manganese being abundant and relatively
inexpensive compared with nickel and cobalt
Ni
NCM 622
Co
NCM 523
Li
NCM 307
Emerging
manganese rich
battery
configurations
Fe
NCM 217
P
NCM 111
LMFP
LMO
0
0.2
0.4
0.6
Source: Benchmark Mineral Intelligence and company research
0.8
1
1.2
1.4
5
CURRENT TRENDS
IN CATHODE
DEVELOPMENT
Source: Company research
September Suzhou Conference Highlights
Leading researchers and companies showcased the latest developments and new products in manganesebased battery technology
Key Areas of Focus
•
Current Trends: Continued advancement of Lithium Manganese Oxide (LMO), a widely used Li-ion cathode
for over 15 years. Efforts are also underway to increase manganese content in ternary cathodes
•
Short to Medium Term: Lithium Manganese Iron Phosphate (LMFP) is rapidly emerging as an upgrade from
LFP. LMFP is now commonly used in two-wheel vehicles and mixed with ternary cathodes (e.g., CATL M3P)
in EVs, with a shift towards standalone use in EVs
•
Future Outlook: Li-rich and Mn-rich (LMR) cathodes are expected to play a pivotal role in solid-state
batteries, as manganese is uniquely suited for these advanced cathode materials
SUCCESSFULLY ESTABLISHING A
BATTERY GRADE MANGANESE
OPERATION IN CHINA
INDUSTRY-LEADING MANGANESE EXPERTISE
•
Proven Track Record - Since listing in 2021, Firebird has focused exclusively on
developing a world-class manganese business. The team has consistently met its
objectives on time and within budget, driven by a vision to become a fully integrated
manganese battery material leader
•
•
Leadership Team
o
Peter Allen, Managing Director: Over 20 years of experience in marketing and
developing manganese projects, providing strategic direction and industry insights
o
Wei Li, Executive Director & Managing Director of China Operations: Expert in
manganese battery material business, instrumental in commissioning a A$150
million Electrolytic Manganese Dioxide (EMD) plant in Hunan, China
Key Technical Experts
o
o
•
Mr. Zhou Qiyun, Chief Technical Officer: 20 years’ experience in battery grade
MnSO4 production. Co-owned a 10,000 tonne/year MnSO4 plant, and has been
pivotal in optimising and commercialising MnSO4 processing technologies, holding
a number of patents
BOARD & MANAGEMENT
EVAN CRANSTON
Non-Executive Chairperson
PETER ALLEN
Managing Director
WEI LI
Executive Director
ASHLEY PATTISON
Non-Executive
Director
BRETT GROSVENOR
Non-Executive
Director
CHINA IN-COUNTRY TEAM
HUNAN FIREBIRD BATTERY TECHNOLOGY (HFBT)
WEI LI
Managing Director
Mr. Tang Min, Operations Manager: Extensive experience in the design,
engineering, and operation of MVR and sulphate production systems
Collaborative R&D Efforts - Professors Ou and Ming bring extensive industry
experience, having worked on numerous real-world projects, including serving as the Chief
Technical Officer for LFP development between 2010 and 2014. More recently, they played
a key role in establishing and listing Pa Wa Gu Fen (Stock Code 688184, POWER), a
Shenzhen-listed company focused on ternary-based cathodes
PROFESSOR
MING LEI
Central South
University
MR ZHOU QIYUN
Chief Technical Officer
MR TANG MIN
Operations Manager
PROFESSOR
OU XING
Central South
University
8
STRATEGIC LOCATION – JINSHI
HIGH-TECH INDUSTRIAL PARK
•
Premier Chemical Industrial Hub: Jinshi High-Tech Industrial Park
is one of the top-rated parks in Hunan Province, known for its
exceptional services and state-of-the-art facilities
•
Strategic Connectivity: Located on the Lishui River, the park
connects directly to the Yangtze River, with a bulk terminal
capacity exceeding 10 million tonnes per annum, ensuring
seamless logistics and transportation
•
World-Class Infrastructure: The park offers access to critical
infrastructure, including a steam plant, dual power lines, a water
treatment facility, and a cement plant depot, supporting diverse
industrial needs
•
Competitive Advantages: Firebird benefits from highly attractive
land prices and tax incentives, receiving better terms than any
other company in the park. The company also qualifies for all
available Chinese domestic grants
•
Supportive Business Environment: The park receives robust
support from all levels of governments, particularly for foreign
investment initiatives, making it an ideal location for international
business expansion
•
Thriving Industrial Community: Over 100 companies are currently
operating in the park. Several new businesses have established
pilot plants within the development area
9
ASX: FRB
AERIAL VIEW OF
PROPOSED PLANT
•
Preliminary design and key permits
secured in less than 12 months
•
Production Capacity – Battery grade
50kt MnSO4 plus 10kt Mn3O4, (72.5Kt
MnSO4 equivalent)
•
12.09 hectares land with 84,399sqm
building area
•
>5,000 sqm land available on site for
future expansion
•
Firebird can build the proposed plant
in less than 12 months from making
FID - a key advantage of establishing
operations in China
Refer ASX announcements 7/5/24, 2/10/24
10
Precipitation & Filter Press Plant
Water Treatment Plant
Ore & Tailing Storage, Calcining Kiln
Mn3O4 Plant
Office, R&D Facility, Central Control
Crystallisation & Packaging
Refer ASX announcement 2/10/24
LEADING PROJECT ECONOMICS – LOW-COST
PATHWAY TO PRODUCTION
•
•
•
•
Project Economics: Feasibility Study outlined a significant opportunity to establish a
near-term, cost-competitive, battery-grade manganese sulphate operation
•
Low Capital Expenditure (CAPEX): US$83.5 million
•
Working Capital: US$10.7 million
•
Plant Capacity: Producing 50,000 tonnes per annum (t/a) of battery-grade MnSO4 and
10,000 t/a of Mn3O4, or an equivalent of 72,500 t/a of MnSO4
•
Sustainable Process: The facility is designed to be environmentally friendly, generating no
wastewater and ensuring all residues are utilised by a cement plant
Operational Efficiency: The project’s operational expenses (OPEX) are very
competitive with peers in China and do not depend on subsidies from joint venture
partners or the government, underscoring the project’s economic viability
Financing Secured: Approximately 60% of the required financing has been secured
through indicative and non-binding agreements with key partners, including China
Chemical and China Construction Bank
CAPEX US$83.5M + Working Capital US$10.7M
Equity
China
Construction
Bank - CAPEX
Permits and Approvals:
•
All critical permits, including environmental, safety, and energy permits, have been obtained
since the establishment of Hunan Firebird Battery Technology Co., Ltd in November 2023
•
Preliminary design has been completed and approved by the Jinshi High-Tech Industrial Park
Committee, covering roughly 80% of the requirements for the building permit
•
The building permit is expected to be granted shortly after the completion of the detailed
engineering design
Refer ASX announcements 7/5/24, 14/5/24, 28/5/24,10/9/24 and 24/9/24
China Chemical CAPEX deferred
payment
China
Construction Bank
- Working Capital
12
PEER COMPARISON
Firebird Metals
(ASX: FRB)
Element 25 Train 1
(ASX: E25)
Euro Manganese
(ASX:EMN, TSXV: EMN, OTCQB: EUMNF)
Study Complete
Feasibility Study
Feasibility Study
Feasibility Study
Production Capacity
72,500 t/a HPMSM
65,000 t/a HPMSM
100,000 t/a HPMSM & 15,000 t/a HPEMM
Products
50,000 t/a HPMSM & 10,000 t/a Mn3O4
65,000 t/a HPMSM
100,000 t/a HPMSM & 15,000 t/a HPEMM
Capital
US$82.3 M
US$289 M
US$757.3 M
US$609 per tonne product
US$579 per tonne product (with kiln cost savings)
US$1,294 per tonne product
US$214.54 per tonne of dry plant feed
Tonnes of feed processed
66,000 t/a
~72,000 t/a
1,066,000 t/a
HPMSM Price Assumption
US$1419
Not Disclosed
US$4,019
Cathode Development plans
Yes
100% treated by cement plant
"The net result of the flowsheet design is that the solid by
products are removed via the production of three coproduct
streams that can be repurposed in other industrial
applications thereby largely eliminating the need for a solid
waste landform as part of the Facility"
"Returning washed tailings to the carefully prepared
containment cells in the excavated areas of the tailings
progressively remediates the environmental impact risks of
legacy mining operations"
Environmental, Energy and Safety Permit Received
all received in less than 1 year
Air Permit received
Environmental (ESIA) received
No
No
No
Production Cost
Solid Waste
Permits
Sulphate Commercial Production / FID
Sources: See slide in reference
13
LOW-COST AND STRONG ECONOMIC PROFILE
PROCESS FLOW DIAGRAM – SIMPLE & EFFECTIVE
•
Efficient and Cost-Effective Operations:
Firebird’s Chinese technical team has
developed a process with low capital intensity
and operational costs, demonstrating their
expertise in the field
•
Sustainable and Eco-Friendly: The process is
designed to be environmentally sustainable,
ensuring that all residues are either consumed
or sold, minimising waste and environmental
impact
•
Innovative Proprietary Technology: The
project is supported by proprietary technology
specifically aimed at reducing operational
expenses (OPEX), enhancing overall cost
efficiency and competitiveness
For full details refer to ASX announcement dated 7/5/24
15
RESEARCH & DEVELOPMENT LAB
• R&D Lab Completed Early: Firebird successfully completed the construction of its Research and Development lab in January 2024, ahead of
schedule and under budget
• Pilot Plant in Operation: Producing samples of MnSO4 and Mn3O4 for evaluation by potential customers and offtake partners
• Showcasing to Financiers: The pilot plant will also serve as a demonstration facility, showcasing the production process to potential
financiers and stakeholders
• Expanding Research Capabilities: The R&D lab will be instrumental in testing and developing additional manganese-rich Cathode Active
Materials (CAM), driving further innovation and product development
• Video of Firebird Lab
For full details refer to ASX announcement dated 29/1/24
16
WORLD’S MOST ENERGY-EFFICIENT MANGANESE REDUCTION
ROASTING KILN
•
Innovative Technology for Reduced Energy Consumption: Traditional Manganese
calcining technology requires a minimum of 300 kWh per tonne of feed, heating
materials to 900°C and then cooling with water and air, leading to significant energy loss
•
Revolutionary Energy-Saving Solution: Firebird’s proprietary technology, currently
under patent application, recycles heat from the calcined material to pre-heat incoming
feed, drastically cutting energy usage and boosting the cost-efficiency of its high-purity
manganese sulphate plant
•
Strategic Partnership with Sunward: Firebird entered a development agreement with
Zhongji Sunward Technology Co., Ltd, a prominent producer of rotary tunnel kilns in
China. Sunward will pay a 5% royalty on future sales revenue for using this innovative
technology
•
Versatile Industrial Applications: The energy-saving rotary kiln technology is adaptable
for various industrial uses, including iron ore beneficiation and lithium sulphate
production
•
Promising Pilot Plant Results: Following internal trials and independent reports from
Sunward, the kiln demonstrated remarkable energy savings. Compared to conventional
kilns, which typically require more than 300 kWh1 per tonne of feed, Firebird s pilot kiln
operates at only 80-100 kWh per tonne — delivering 70% in energy savings
•
Detailed 3D Design of Firebird’s Rotary Kiln
Path to Commercialisation: The pilot plant’s energy consumption is already lower than
that of a full-sized conventional kiln. This indicates that a scaled-up version of the
Firebird kiln will be even more efficient. Firebird and Sunward are collaborating closely
to commercialise this groundbreaking technology
For full details refer to ASX announcement dated 5/6/24, 12/9/24 and 21/10/24
17
Speed of Development
• R&D – 1 month
KILN TESTING
• Design – 1 month
• Engineering – 1 month
• Fabrication and installation – 1 month
• Testing and reporting – 1 month
• Minimum 70% energy reduction
For full details refer to ASX announcement dated 5/6/24, 12/9/24 and 21/10/24
18
WORLD-LEADING 5TH GENERATION CONTINUOUS HIGHPRESSURE CRYSTALLISATION REACTOR
1st
2nd
3rd
1st generation Single effect evaporator
•Indirect heating to concentrate solution
2nd generation Multi-effect evaporator
•60% energy use of 1st generation
•Recycle residual heating to pre-heat incoming solution
3rd generation MVR
•40% energy use of 1st generation
•More efficient heating and recycle energy
4th generation Single High pressure, high temperature reactor
4th
5th
•
•25% energy use of 1st generation
•Like a pressure cooker, efficiency improved due to high
pressure and temperature
5th generation (patent technology) Continuous high-pressure
system, 8% energy use of 1st generation
•1/3 energy use of 4th generation
•Based on 4th generation system, it operates continuously
& residual energy is used in pre-heating feed solutions
•
•
Current Industry Standard: Most companies are still utilising 1st to
4th generation technologies for sulphate production
Advanced 5th Generation Technology: Firebird’s 5th generation
technology is already in successful commercial use, with three units
sold to date
Significant Steam Savings: Steam is a major cost factor in sulphate
production. This advanced technology is expected to reduce steam
consumption to less than half of the industry average, greatly
improving cost efficiency
For full details refer to ASX announcement dated 7/5/24
19
WHY CHINA FIRST? A STRATEGIC CHOICE FOR THE FUTURE
•
•
•
•
•
Dominant Electric Vehicle Market: China became the largest car exporter in 2023, with electric vehicles
(EVs) making up nearly all of these exports. Half of all new car sales in China are EVs, and this percentage
continues to grow
Technological Leadership: China’s EV battery development is estimated to be at least a decade ahead of
Western competitors. Western manufacturers are delaying expansion due to high costs, outdated
technology, and a fragmented supply chain
Unmatched Industrial Efficiency: China boasts the world’s most efficient industrial supply chain,
supported by a vast, skilled workforce and high production standards. The government is committed to
environmental sustainability and streamlining project permits
Strategic Positioning of Firebird: A key objective of Firebird is to establish a profitable manganese-based
cathode material business, leveraging its unique process and technology. This model can be replicated
globally
Investor Confidence: Professional investors visiting Firebird’s Chinese operations have been highly
impressed by the rapid progress delivered, quality of work at the Jinshi High-Tech Industrial Park, extensive
relationships developed, support for the Company and the overall business environment in China
Source: Company research
20
HUNAN IS AT THE EPICENTRE OF CHINESE MNSO4 DEMAND
21
LMFP WITH CENTRAL SOUTH UNIVERSITY
HOW DOES FIREBIRD CAPTURE THE WAVE OF THE NEXT-GEN
LI-ION BATTERIES?
• FRB’s vision is to combine its traditional mining business with downstream processing
and grow into a global cathode producer
• Firebird has a strategic advantage on integrating MnSO4 into LMFP production
•
Crystallisation is a major operational cost in MnSO4 production, even with Firebird’s patented
5th Generation Crystallisation technology
•
Typical LMFP production involves purchasing MnSO4, dissolving it and wasting energy from the
crystallization process
•
Firebird’s method eliminates this inefficiency, offering a significant cost advantage in LMFP
production
•
Importantly, Firebird’s technology is transferable to locations outside of China
• Lab Testing, Internal Scoping Study, and Commercial-Sized Pilot Plant
•
Firebird will start lab-testing soon, with specialist equipment already ordered
•
An internal Scoping Study is underway to prepare for a Pilot Plant capable of producing one
metric tonne of LMFP per day
•
CSU professors and their team have developed a solid foundation in LMFP production
•
Lab testing with Firebird’s technical team will refine the production process, which differs from
mainstream methods
•
Firebird plans to patent aspects of the production process both in China and internationally
• Industry Developments:
•
CATL Acquisition: CATL purchased Lithitech, valuing the company at US$131 million in
2021, for its 2,000 tonne per annum LMFP production and expansion plans
•
LOPAL Acquisition: LOPAL, through its subsidiary, acquired BEITERUI, an LMFP technology
company, for US$119 million in December 2020
Source: Company research
For full details refer to ASX announcement dated 28/10/24
23
RESOURCES
OAKOVER PROJECT
Over the medium to long term, Oakover will play an integral role in the
delivery of Firebird’s manganese battery material strategy
KEY HIGHLIGHTS
PORT HEDLAND
• Near-surface, gently dipping geology
• Metallurgical test work demonstrated saleable 30 - 32% Mn concentrate product
achievable
• Hydrometallurgy test work demonstrated Battery Grade MnSO4 achievable
NEWMAN
• Updated DMS Manganese Concentrate Scoping Study generated strong results and
highlighted Oakover as a long-life, high-quality operation:
1
WESTERN
AUSTRALIA
• 18-year Life of Mine
• ~A$741.3 M NPV at a discount rate of 8%
• Impressive IRR of 73.1%
• CAPEX of A$123M
Mineral Resource
Classification
Tonnes (Mt)
Mn
Share your feedback