Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
22 January 2026
DECEMBER 2025 QUARTERLY ACTIVITIES REPORT
Q4 CY2025 Highlights
• MFP precursor CAM exceeds China industry benchmarks. Internal and third-party
test work demonstrates that all key technical and performance parameters exceed
Chinese industry standards T/CIAPS0029-2023, including ~33% lower impurity, ~25%
higher tap density and higher 0.1C/1C specific capacities. These results are based on
150+ test batches (producing ~200kg of product) and supported by 30kg of material
already supplied to a potential LMFP cathode customer.
• Energy‑saving kiln patent secured, ADP development advanced. Firebird was
granted a core equipment‑design patent for its proprietary high‑efficiency kiln
(demonstrating up to 70% energy savings) and has significantly progressed planning
for the Australian Demonstration Plant (ADP) to showcase end‑to‑end production of
HPMSM, LMFP precursor (p-CAM) and CAM materials outside China.
• Board and management changes to support execution. Experienced battery
industry executive Ron Mitchell was appointed Chief Executive Officer, Evan Cranston
transitioned to Executive Chairman, and Peter Allen stepped down as Managing
Director and moved to a consulting role.
• Cash: At 31 December 2025 was A$5.16 million
Manganese Battery Market Update
• Growing global momentum for manganese-rich cathodes, with major OEMs
(including Ford and GM) signalling plans to commercialise LMR chemistries by 2030,
LMFP adoption continuing to expand in EV and ESS markets, and OEM presentations
(e.g. GM at AABC Dec-2025) highlighting LMR’s combination of higher voltage,
improved energy density and lower cell cost.
Figure 1: LMFP coin-cell batteries incorporating Firebird’s proprietary battery materials.
2
Australian-owned Firebird Metals Limited (ASX: FRB, Firebird or the Company) is
pleased to provide an update on its activities for the quarter ended 31 December 2025
(the Quarter). During the Quarter, Firebird advanced its manganese‑rich battery strategy
through continued LMFP precursor development and progressed key technology
commercialisation initiatives, including securing patent protection for its energy‑saving
kiln and advancing planning for an Australian Demonstration Plant (ADP) to support
Western market entry.
Firebird is developing a fully integrated manganese-rich battery materials platform
spanning manganese feedstocks to high-purity manganese sulphate monohydrate
(HPMSM), precursor cathode materials (p-CAM) and cathode active materials (CAM)
including lithium manganese iron phosphate (LMFP) and lithium manganese rich (LMR) for
EVs and energy storage. This integrated, solution-based platform underpins a
differentiated investment proposition, delivering the following strategic advantages:
• Structural cost advantage through solution-based co-synthesis of p-CAM
directly from HPMS.
• Aligned with OEM priorities of cost, performance and safety via manganese-
rich cathode chemistries.
• Exposure to high-growth EV chemistries: LMFP (next-gen LFP) and LMR (next-
gen high-energy layered oxide).
• Capital-light scale-up via demonstration, customer qualification and
commercial partnering (licensing/equipment and product sales/strategic JVs).
Firebird CEO, Mr Ron Mitchell, commented:
“During the December quarter, Firebird delivered meaningful progress towards advancing our
world first manganese based advanced battery materials development strategy. Securing key
patent protection for our energy‑saving kiln strengthens the Company’s equipment and
proprietary process commercialisation pathway, while our MFP precursor program achieved
performance improvements exceeding China industry standards and progressed customer
sampling. With the ADP planning and site selection work advancing, we are focused on
crystallising these technical milestones into partnerships and commercial revenue-based
outcomes as we build an end‑to‑end ‘concentrate to cathode’ pathway for Western markets.”
Manganese-Rich Battery Strategy (LMFP & LMR)
MFP precursor program – performance improvement and customer sampling
On 10 December 2025, Firebird reported that its manganese iron phosphate (MFP)
precursor cathode active material (p-CAM) achieved performance improvements over
multiple parameters relative to China’s industry standards (T/CIAPS0029‑2023),
supported by both internal and independent testing. Firebird completed more than 150
individual test batches, producing approximately 200 kg of MFP p-CAM, and supplied 30
kg to a potential downstream customer for LMFP cathode production, with initial coin‑cell
testing indicating strong performance.
Firebird’s approach leverages proprietary high‑purity manganese sulphate (HPMS)
production technology to use HPMS in solution prior to crystallisation, enabling
3
co‑precipitation of the MFP precursor without an intermediate crystallisation step. The
Company highlighted advantages including lower raw‑material costs, reduced
capex/opex through reduced unit operations, and improved precursor quality via tighter
atomic‑level Mn:Fe ratio control. The process is designed to be scalable and aligned with
contemporary cathode manufacturing requirements, supporting the Company’s focus on
commercialisation outside China.
Production of MFP p-CAM, LMFP CAM and other high‑purity battery materials is targeted
at Firebird’s planned Australian Demonstration Plant (ADP) in 2026. The ADP is intended
to provide a practical commercialisation pathway from manganese concentrate to LMFP
cathode materials tailored to Western markets, including sample generation for customer
qualification and the technical foundation for a commercialisation platform.
Figure 2: The Company’s precursor LMFP testing results compared with China industry standards
T/CIAPS0029—20231
and customer requirements.
Kiln Development & Technology Commercialisation
Energy‑saving kiln patent secured
On 28 November 2025, Firebird announced the award of an equipment‑design patent
(Patent No. ZL202422926714.7) covering its proprietary energy‑efficient rotary kiln
system, including key features such as inner/outer tubes, a screw‑type discharge cooler
and sealed feeding mechanisms. The Company reported that the kiln has demonstrated
up to 70% energy savings on high‑grade manganese ore and supports Firebird’s
integrated concentrate‑to‑battery‑materials flowsheet.
The patented kiln also supports a near‑term commercial pathway via equipment supply
and technology licensing. Firebird noted the kiln design remains the subject of an
expression of interest (EOI) from Taza Metal Technologies to purchase up to five kilns
following successful test work, with potential revenue exceeding US$10 million, to be
fabricated by partner Zhongji Sunward. Firebird also highlighted the potential
1
Tested as per Chinese standard T/CIAPS0029—2023 Appendix C.6 Specific capacity tested at 25 degrees celcius and 4.5 volts.
4
applicability of the kiln’s high‑efficiency electric calcination principles across other
downstream industries.
Figure 3: The Company’s High-Efficiency Energy-Saving Roasting and Drying Kiln located at Firebird’s 100%
owned subsidiary laboratory in Hunan, China.
Australian Demonstration Plant (ADP) – pathway to Western markets
In conjunction with the kiln patent announcement, Firebird provided an update on its
planned Australian Demonstration Plant (ADP). The ADP is intended to showcase the
Company’s end‑to‑end conversion of manganese concentrate into HPMSM, LMFP
precursor (p-CAM) and LMFP cathode active material (CAM), using Firebird’s patented and
proprietary equipment and processing techniques. Firebird stated the ADP will integrate
China‑developed engineering and process know‑how with Western engineering, safety
and regulatory standards to create deployment‑ready technology for Australian and
international markets.
The Company reported that a formal ADP site‑selection process is underway, targeting a
capital‑light, multi‑year lease of an existing structure within a light‑industrial precinct in
the Perth metropolitan area. Firebird intends to leverage potential Australian
5
Government support programs for downstream battery‑materials demonstration
projects and is already engaging with Western OEMs, battery and cathode manufacturers
to support sample qualification and commercial partnership discussions.
Firebird outlined multiple potential Western‑market revenue streams linked to the ADP,
including technology licensing, equipment supply, and downstream production of
advanced battery materials. The ADP is also intended to act as a training and
knowledge‑transfer hub to build local capability in precursor and CAM production, while
supporting customer‑specific R&D and further IP development within Australia.
Figure 4: The ADP production process pathway showing patented technology, intellectual property and
expertise leading to the production of a variety of manganese-based battery materials.
About Firebird’s Solution-Based Co-Synthesis
Firebird’s proprietary, patent‑backed, solution‑based co‑synthesis retains high‑purity
manganese sulphate (HPMS) in solution and directly synthesises precursor cathode
material (p‑CAM). This structurally removes conventional steps such as HPMS
crystallisation, drying, transport, re‑dissolution and dry‑state blending - simplifying
flowsheets, reducing energy intensity and improving compositional control.
Firebird has developed a world first integrated ore-to-cathode capability spanning
hydrometallurgy, purification, p-CAM and CAM manufacture. Firebird’s end‑to‑end
process has been proven across multiple process campaigns at its wholly owned pilot
plant in China and is supported by a growing IP portfolio spanning energy‑efficient kiln
technology, advanced crystallisation and cathode material innovations. The Company’s
ore‑agnostic process design enables flexibility to use a range of manganese feedstocks
delivering battery‑grade specifications.
Figure 5: Firebird’s proprietary solution-based co-synthesis process
6
Corporate
Board and management changes
On 27 October 2025, Firebird announced the appointment of Mr Ron Mitchell as Chief
Executive Officer, with Mr Evan Cranston transitioning to Executive Chairman (both
effective 3 November 2025). Managing Director Mr Peter Allen stepped down from the
role effective 31 October 2025 and transitioned to a consulting role to support continuity
as Firebird progresses its HPMS and LMFP strategy.
Mr Mitchell brings more than 25 years of senior commercial, strategy, sales and business
development experience, including 15 years across lithium, battery materials and critical
minerals. His experience includes senior executive and board‑level roles across the global
battery value chain, including key leadership roles at Global Lithium Resources, Tianqi
Lithium and Talison Lithium, and serving as the inaugural Chairman of the London Metal
Exchange (LME) Lithium and Cobalt Committee.
Firebird advised key executive terms including base remuneration and participation in
short‑ and long‑term incentive arrangements and confirmed Mr Allen would provide
full‑time consulting for an initial period before reducing to part‑time support. These
changes were positioned to strengthen execution capability as the Company advances
ADP planning, battery‑materials development and commercial engagement in both China
and Western markets.
Figure 6: Firebird Metals new CEO, Ron Mitchell.
7
Oakover Manganese Project, Western Australia
Oakover is Firebird’s strategic upstream JORC resource intended to secure
long-term manganese supply for the battery materials business. The
project hosts favourable, near-surface mineralisation and prior
metallurgical test work has demonstrated the potential to produce
battery-grade feed.
No activity was undertaken at the Oakover Project during the quarter, with
work limited to tenure maintenance and desktop planning while focus
remained on downstream proprietary LMFP/LMR and kiln initiatives.
Manganese Battery Market Update
Momentum for manganese-rich cathodes continues to build globally as EV and energy-
storage customers prioritise safer, lower-cost and higher-performance chemistries.
Major OEMs, including Ford and General Motors, have publicly announced plans to
commercialise LMR cathodes for next-generation EVs by 2030, while LMFP adoption
continues to grow across EV and ESS markets.
LMR is widely anticipated to deliver a compelling blend of performance, safety, cost and
supply-chain benefits relative to conventional lithium-ion cathodes. These include the
potential for higher energy density than LFP, improved thermal stability versus high-
nickel chemistries, and a more resilient raw-materials mix through high manganese
substitution (≥50% Mn) that reduces reliance on nickel and cobalt. Importantly, LMR is
also expected to be manufacturing compatible, enabling adoption through evolutionary
changes to existing cathode production facilities, supported by rapid technical progress
in doping, coatings, particle engineering and electrolyte optimisation.
Recent OEM messaging has reinforced this technology trend. During the Advanced
Automotive Battery Conference (AABC) in Las Vegas (8–11 December 2025), General
Motors publicly stated its preference for LMR technology, citing higher operating voltage,
improved energy density and lower overall cell cost (Figure 7). Against this backdrop,
Firebird’s integrated concentrate-to-HPMSM-to-LMFP/LMR platform and planned
Australian Demonstration Plant are well aligned to leverage from accelerating demand
for manganese-rich cathode materials and Western supply-chain diversification.
8
Figure 7: Slide from General Motors’ presentation at the 25th Advanced Automotive Battery Conference
(AABC) Dec 2025.
Figure 8: Firebird’s LMR CAM production process flow.
9
Outlook & Near-Term Priorities (Q1 CY2026)
• Scale MFP/LMFP qualification program: Increase batch production of MFP p-
CAM for LMFP cathode testing, expand coin‑cell work into larger‑format cells
where appropriate, and deliver additional samples to Chinese and Western
cathode/battery customers to progress formal qualification programs.
• Advance ADP site and engineering: Finalise site selection and commercial terms
for the Australian Demonstration Plant (ADP), progress front‑end engineering and
permitting, and refine the staged capex/schedule to support 2026 commissioning
and customer‑focused sample generation.
• Convert kiln IP into binding contracts: Use the newly granted energy‑saving kiln
patent and existing EOI momentum to advance detailed engineering and
commercial negotiations with Taza Metal Technologies in relation to binding kiln
purchase agreements, while undertaking business development activities
focussed on additional commercial opportunities for the kiln technology in the
manganese and other complementary industries including the lithium sector.
• Strengthen partnering and commercial funding pathways: Deepen
engagement with OEMs, cathode and battery makers and strategic investors in
Western markets. Review revenue and commercial business models to assess the
best commercialisation pathway for Firebird’s technology with a focus of
maximising shareholder value.
• Progress the Australian Demonstration Plant (ADP): Finalise a preferred site
and execute a binding lease agreement. Pursue potential Australian Government
grant funding opportunities and incentive programs to support ADP capex and
ongoing R&D. Finalise negotiations with key equipment suppliers and initiate ADP
equipment orders.
• Maintain upstream development optionality: Continue desktop technical
studies and market monitoring for Oakover and the Company’s broader WA
manganese portfolio, ensuring alignment with future downstream
HPMSM/LMFP/LMR demand and commercial partnership requirements.
Quarterly Cashflow Disclosures
The Appendix 5B for the quarter ended 31 December 2025 provides an overview of the
Company’s financial activities.
Exploration expenditure for the Quarter was approximately $224,000 and primarily
related to environmental work and consulting fees.
Expenditure related to the development of the Chinese manganese sulphate plant and
Mn3O4 plant was approximately $129,000
The total amount paid to Directors of the Company, their associated and other related
parties was $504,000 comprising salary, Directors’ fees and rent.
Cash and cash equivalents at Quarter end were approximately $5.16 million.
10
- END -
This announcement has been approved for release by the Board.
For further information contact:
Ron Mitchell Gigi Penna
CEO Investor Relations
ron.mitchell@firebirdmetals.com.au +61 404 147 568
+61 407 726 325 FRB@calderahouse.com.au
About Firebird Metals Limited (ASX:FRB)
Firebird Metals is developing an Australian ore‑to‑cathode strategy for manganese‑rich
lithium‑ion cathode materials, spanning manganese feedstocks through to HPMSM,
p‑CAM and cathode active material (CAM) for high‑growth chemistries including LMFP
and LMR.
A WA‑based Australian Demonstration Plant (ADP), planned for commissioning in 2026,
is intended to validate end‑to‑end conversion of manganese feedstocks into HPMSM,
p‑CAM and CAM and to support customer qualification through representative product
sampling.
Upstream optionality is provided by the wholly owned Oakover Manganese Project in
Western Australia (JORC Mineral Resource: 176.65 Mt at 9.9% Mn; mining lease granted2
),
underpinning long‑term concentrate supply.
JORC Compliance Statement
This announcement contains references to Mineral Resource Estimates, which have been
reported in compliance with Listing Rule 5.8 and extracted from previous ASX
announcements as referenced. The Company confirms that it is not aware of any new
information or data that materially affects the information previously reported and that
all material assumptions and technical parameters underpinning the Mineral Resource
Estimates continue to apply and have not materially changed.
Announcements made during the Quarter:
Date Announcement
27-Oct-25 Board and Management Changes (Ron Mitchell appointed CEO)
28-Nov-25 Firebird Secures Energy‑Saving Kiln Patent; ADP Update
10-Dec-25 Firebird MFP Precursor CAM Outperforms China Industry Standards
2
For full details refer to ASX announcements 10/3/22, 30/1/23, 23/3/23, 26/6/23 and 30/8/23. Indicated Resource of 105.8Mt at 10.1%;
Inferred Resource of 70.9Mt at 9.6% for global Resource of 176.7 Mt at 9.9% Mn.
11
Additional Listing Rule Information
The Company advises the following information in accordance with Listing Rule 5.3.3 as
at 31 December 2025:
Western Australian
Project
Tenement Ownership at the
Start of quarter
Ownership at end of
Quarter
Oakover E 52/3577 100% 100%
Oakover E 46/1392 100% 100%
Oakover E 52/3948 100% 100%
Oakover E 46/1570 100% 100%
Hill 616 E 52/3633 100% 100%
Wandanya E 46/1456 20% 20%
Forward Looking Statements
This announcement may contain certain “forward-looking statements”. Forward looking
statements can generally be identified by the use of forward-looking words such as,
“expect”, “should”, “could”, “may”, “predict”, “plan”, “will”, “believe”, “forecast”, “estimate”,
“target” and other similar expressions. Indications of, and guidance on, future earnings
and financial position and performance are also forward-looking statements. Forward-
looking statements, opinions and estimates provided in this presentation are based on
assumptions and contingencies which are subject to change without notice, as are
statements about market and industry trends, which are based on interpretations of
current market conditions. Forward-looking statements including projections, guidance
on future earnings and estimates are provided as a general guide only and should not be
relied upon as an indication or guarantee of future performance.
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Firebird Metals Limited
ABN Quarter ended (“current quarter”)
24 610 035 535 31 December 2025
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(6 months)
$A’000
1. Cash flows from operating activities
1.1 Receipts from customers
1.2 Payments for
(187) (239)
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (504) (646)
(e) administration and corporate costs (686) (942)
1.3 Dividends received (see note 3) - -
1.4 Interest received - -
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (GST refunds) 39 74
1.9 Net cash from / (used in) operating
activities
(1,338) (1,753)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment (204) (231)
(d) exploration & evaluation (37) (54)
(e) investments - MnSO4+Mn3O4 plant
China
(129) (277)
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(6 months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material) - -
2.6 Net cash from / (used in) investing
activities
(370) (562)
3. Cash flows from financing activities
5,945 5,945
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
(334) (334)
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings (12) (29)
3.7 Transaction costs related to loans and
borrowings
- (1)
3.8 Dividends paid - -
3.9 Other - 392
3.10 Net cash from / (used in) financing
activities
5,599 5,973
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
1,269 1,502
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(1,338) (1,753)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
(370) (562)
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
5,599 5,973
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(6 months)
$A’000
4.5 Effect of movement in exchange rates on
cash held
- -
4.6 Cash and cash equivalents at end of
period
5,160 5,160
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 5,160 1,269
5.2 Call deposits - -
5.3 Bank overdrafts - -
5.4 Other (provide details) - -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
5,160 1,269
6. Payments to related parties of the entity and their
associates
Current quarter
$A’000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
484
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
-
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 4
+ See chapter 19 of the ASX Listing Rules for defined terms.
7. Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities n/a n/a
7.2 Credit standby arrangements n/a n/a
7.3 Other (please specify) n/a n/a
7.4 Total financing facilities
7.5 Unused financing facilities available at quarter end n/a
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
n/a
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (item 1.9) (1,338)
8.2 (Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
(370)
8.3 Total relevant outgoings (item 8.1 + item 8.2) (1,708)
8.4 Cash and cash equivalents at quarter end (item 4.6) 5,160
8.5 Unused finance facilities available at quarter end (item 7.5) -
8.6 Total available funding (item 8.4 + item 8.5) 5,160
8.7 Estimated quarters of funding available (item 8.6 divided by
item 8.3)
3.02
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8 If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1 Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: n/a
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: n/a
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 5
+ See chapter 19 of the ASX Listing Rules for defined terms.
8.8.3 Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: n/a
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1 This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2 This statement gives a true and fair view of the matters disclosed.
22 January 2026
Date: ...................................................................................
By the Board
Authorised by: ...................................................................................
(Name of body or officer authorising release – see note 4)
Notes
1. This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2. If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash
Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3. Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4. If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the
[name of board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclosure committee, you can insert here: “By the Disclosure Committee”.
5. If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and
Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the appropriate accounting standards
and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a
sound system of risk management and internal control which is operating effectively.