Firebird Investor Presentation RIU Sydney Resources Roundup
Released
Released
Announcement PDF
FIREBIRD METALS – AUSTRALIA’S
NEXT BATTERY TECH COMPANY
May 2025
ASX:FRB
DISCLAIMER
CAUTIONARY STATEMENT – SULPHATE FEASIBILITY STUDY
This presentation contains summary information about Firebird Metals Limited (Firebird) (ABN 24 610 035 535) and is current
as of 6 May 2025. The information in this presentation is of a general background and does not purport to be complete. This
presentation is not investment or financial product advice (nor tax, accounting or legal advice) and is not intended to be used
for the basis of making an investment decision.
The Feasibility Study referred to in this presentation is a Technical Feasibility of the establishment of the Battery Grade
Manganese Sulphate Project Stage 1 Processing Plant in China (the Plant). The Feasibility Study is based on the material
assumptions contained in the Feasibility Study document released to the ASX on 7 May 2024. These include assumptions about
the availability of funding. While the Company considers all of the material assumptions to be based on reasonable grounds,
there is no certainty that they will prove to be correct or that the range of outcomes indicated by the Feasibility Study will be
achieved.
The information contained in this presentation has been prepared without taking into account the objectives, financial
situation or needs of individuals. Investors should obtain their own advice before making any investment decision. Firebird has
prepared this document based on information available to it at the time of preparation. No representation or warranty,
express or implied, is made as to the fairness, accuracy or completeness of the information, opinions and conclusions
contained in this presentation.
This presentation contains certain “forward-looking statements”. Forward looking statements can generally be identified by the
use of forward-looking words such as, “expect”, “should”, “could”, “may”, “predict”, “plan”, “will”, “believe”, “forecast”, “estimate”,
“target” and other similar expressions. Indications of, and guidance on, future earnings and financial position and performance
are also forward-looking statements. Forward- looking statements, opinions and estimates provided in this presentation are
based on assumptions and contingencies which are subject to change without notice, as are statements about market and
industry trends, which are based on interpretations of current market conditions. Forward-looking statements including
projections, guidance on future earnings and estimates are provided as a general guide only and should not be relied upon as
an indication or guarantee of future performance
This presentation contains statements that are subject to risk factors associated with Firebird and the mining exploration
industry. It is believed that the expectations reflected in these statements are reasonable, but they may be affected by a range
of variables which could cause actual results or trends to differ materially. Firebird disclaim any intent or obligation to publicly
update any forward-looking statements, whether as a result of new information, future events or results or otherwise. To the
maximum extent permitted by law, Firebird, their related bodies corporate (as that term is defined in the Corporations Act
2001 (Cth) and the officers, directors, employees, advisers and agents of those entities do not accept any responsibility or
liability including, without limitation, any liability arising from fault or negligence on the part of any person, for any loss arising
from the use of the presentation or its contents or otherwise arising in connection with it.
This presentation has been approved by the Board of Firebird.
JORC Compliance Statement
This announcement contains references to Exploration Results and Mineral Resource Estimates, which have been reported in
compliance with ASX Listing Rules 5.7 and 5.8 and extracted from previous ASX announcements as referenced. The Company
confirms that it is not aware of any new information or data that materially affects the information included in the said
announcements, and in the case of estimates of Mineral Resources, that all material assumptions and technical parameters
underpinning the estimates in the relevant market announcements continue to apply and have not materially changed.
The Company confirms that the material assumptions and technical parameters underpinning the production target disclosed
in the Company's announcement dated 7 May 2024 continue to apply and have not materially changed.
For full details refer to ASX announcements 10/3/22, 30/1/23, 23/3/23, 26/6/23, 30/8/23, 1/9/23, 18/10/23, 21/11/23,
13/12/23, 29/1/24, 13/3/24, 7/5/24, 14/5/24, 28/5/24, 5/6/24, 10/9/24, 12/9/24, 24/9/24, 2/10/24, 21/10/24 and
28/10/24
Oakover Resource: Indicated Resource of 105.8Mt at 10.1%; Inferred Resource of 70.9Mt at 9.6% for global Resource
of 176.7 Mt at 9.9% Mn
Hill 616 Resource: Inferred Resource of 57.5 Mt at 12.2% Mn
Notwithstanding the developments set out in this quarterly report, Investors should note that there is no certainty that the
Company will be able to raise the amount of funding to develop the Plant when needed. It is also possible that such funding
may only be available on terms that may be dilutive to or otherwise affect the value of Company’s existing shares.
It is also possible that the Company could pursue other ‘value realisation’ strategies such as a sale, partial sale or joint venture
of the Plant. If it does, this could materially reduce the Company’s proportionate ownership of the Plant. Given the
uncertainties involved, investors should not make any investment decisions based solely on the results of the Feasibility Study.
CAUTIONARY STATEMENT- DMS CONCENTRATE SCOPING STUDY
The Updated Scoping Study announced to the ASX on 30 August 2023 has been undertaken for the purpose of initial
evaluation of a potential development of the Oakover Manganese Project. The Scoping Study is a preliminary technical and
economic study of the potential viability of the Oakover Manganese Project as a manganese producer. The Scoping Study
outcomes, production target and forecast financial information referred to in this release are based on low accuracy level
technical and economic assessments that are insufficient to support estimation of Ore resources.
The Scoping Study has been completed to a level of accuracy of +/- 35% in line with a scoping level study accuracy. While each
of the JORC modifying factors was considered and applied, there is no certainty of eventual conversion to Ore Reserves or that
the production target itself will be realised. Further exploration and evaluation work and appropriate studies are required
before the Company will be in a position to estimate any Ore Reserves or to provide any assurance of an economic
development case. Accordingly, given the uncertainties involved, investors should not make any investment decisions based
solely on the results of the Scoping Study. Given that the results of the Scoping Study are subject to the qualifications above
(including assumptions as to accuracy), any results reported in this release should be considered as approximates and subject
to variances having regard for the assumptions referred to in this release. The Company has reasonable grounds for
disclosing a Production Target, given that approximately 99% of the Life-of-Mine (LOM) Production Target is in the Indicated
Mineral Resource category, and 1% is in the Inferred Mineral Resource category. The production target stated in this
announcement is based on Firebird’s current expectations of future results or events and should not be relied upon by
investors when making investment decisions. Further evaluation work and studies are required to establish sufficient
confidence that the production target will be met. Firebird confirms that the financial viability of the Oakover Manganese
Project is not dependent on the inclusion of Inferred Resources in the Scoping Study.
The Company considers all the material assumptions in this Study to be based on reasonable grounds. These include
assumptions about the availability of funding. While Firebird considers all of the material assumptions to be based on
reasonable grounds, there is no certainty that they will prove to be correct or that the range of outcomes indicated by the
Scoping Study will be achieved. To achieve the range of potential outcomes indicated in the Scoping Study, funding of in the
order of $123 million (excluding working capital and finance costs) will likely be required. Investors should note that there is no
certainty that Firebird will be able to raise that amount of funding when needed. However, the Company has concluded it has a
reasonable basis for providing the forward-looking statements included in this announcement and believes that it has a
"reasonable basis" to expect it will be able to fund the development of the Project. It is also possible that such funding may
only be available on terms that may be dilutive to or otherwise affect the value of Firebird’s existing shares. It is also possible
that Firebird could pursue other ‘value realisation’ strategies such as a sale, partial sale or joint venture of the project. If it
does, this could materially reduce Firebird’s proportionate ownership of the project. Given the uncertainties involved, investors
should not make any investment decisions based solely on the results of the Scoping Study.
The Mineral Resources underpinning the production target in the Scoping Study have been prepared by a competent person in
accordance with the requirements of the JORC Code (2012). For full details of the Mineral Resources estimate, please refer to
Firebird’s ASX release dated 23 March 2023. Firebird has confirmed that it is not aware of any new information or data that
materially affects the information included in that release. All material assumptions and technical parameters underpinning
the estimates in that ASX release continue to apply and have not materially changed.
2
DELIVERING ON STRATEGY AND VISION
THE FIREBIRD
PURPOSE
As an Australian-owned company, we specialise in the processing and development of battery
cathode raw materials. With a state-of-the-art research and development facility in China and a worldclass technical team with decades of experience, we are committed to innovation. Our goal is to
become a fully integrated cathode manufacturer, delivering advanced solutions worldwide.
Sector-Leading Team
Move Towards
Manganese Rich
Battery Cathodes
Firebird’s battery chemicals team
boasts more than 50 years of
experience in manganese and
chemical production,
strengthened by experts from
China’s Central South University,
bringing unmatched knowledge
in cathode materials.
Across all types of battery
cathodes, manganese is
playing an increasingly vital
role in delivering costeffective cathodes and
batteries to the market.
Unique Lithium
Manganese Iron
Phosphate “LMFP”
Capabilities
Only western company with
the ability to combine High
Purity Manganese Sulphate
& pCAM processors in
solution to produce LMFP
cathode.
Innovative, Low Cost &
Environmentally
Friendly
Potential MnSO4 costs ~50%
lower than industry average.
Our process is designed to be
environmentally sustainable,
ensuring that all residues are
either consumed or sold,
minimising waste and
environmental impact.
3
MOVE TO MANGANESE RICH BATTERY
CATHODE CHEMISTRY
MOVE TOWARDS MANGANESE RICH BATTERY CATHODES
CRITICAL ROLE OF MANGANESE IN LMFP
Cathode chemistry development is increasingly focused on
boosting manganese content
MOVE TOWARDS MN RICH BATTERY CATHODES
Manganese use in batteries will be much higher than even the most ambitious
projections in the past, mainly due to the combination of :
✓ 1. Mid Nickel NCM (Mn between 15 to 20%)
✓ 2. Sodium-ion batteries (Mn ~20%)
✓ 2. LMFP (Mn ~25%)
✓ 3. Lithium Manganese Rich (LMR) (Mn ~ 50%)
✓ 3a. Lithium Manganese Oxide LMO (Mn ~60%)
✓ 3b. Lithium Manganese Nickel Oxide LMNO (Mn ~45%)
Source: Giga Mn newsletter & Magnus Bekker Note: elemental content in cathode
•
Lithium Iron Phosphate (LFP) is the world’s most used Li-ion cathode
material for use in EV batteries
•
Three critical key considerations for battery manufacturers when
assessing and developing a cathode mix is safety, cost and capacity
•
Adding high purity manganese sulphate (MnSO4) to LFP, creates
LMFP (Lithium Manganese Iron Phosphate)
•
LMFP delivers significant operational and safety benefits to a
battery
•
ADVANTAGES OF LMFP VS. LFP & NCM
✓ LMFP has a higher thermal run-away temperature than nickel-based
batteries
✓ LMFP costs ~ 30% of nickel-based batteries
✓ Mn enhances the voltage platform and increases energy density by up to
20%
✓ LMFP is flexible, used on its own or mixed with nickel-based batteries
LMFP is more economical, safer, more flexible, and more energy
dense, making it the future of electric vehicle batteries
5
LMFP MARKET OUTLOOK
Battery Manufacturers
Size and growth of LMFP market for applications in electric vehicle
batteries is potentially the largest in medium to long term (est. avg.
900kg of MnSO4 per 1 tonne of LMFP)
•
McKinsey forecasts global battery share for L(M)FP is expected rise from
11% in 2020 to 44 percent in 2025
•
McKinsey estimate by 2026 that eight of the top automotive groups will
have at least one L(M)FP-equipped vehicle in the volume and premium
segments, up from only a couple of groups in 2023
“Battery technology is on the cusp of a major shift. Our analyses suggest
that L(M)FP batteries could become the technology with the largest global
market share before 2030”
•
Soochow Securities forecast LMFP will replace 50% of LFP batteries by
2030
•
LMFP market is forecasted to become a >US$20 billion market by
2030.
•
Caitong Securities forecast blending LMFP with nickel-based batteries in
China to reach 30% by 2030
Firebird is executing on its battery technology and MnSO4 downstream
processing at the perfect time and will be well-positioned to supply
into this rapidly growing market
Source: Soochow Securities Report 16/8/23, Caitiong Securities report “Cost and performance advantages—LMFP industrialization is imminent” 31/1/2024 and McKinsey “The
Battery Chemistries powering the future of electric vehicles Dec 2024”
Cathode Manufacturers
力泰锂
能
Tesla has stated plans
to have two thirds of
their batteries as
manganese-based
New TESLA Model 3 uses CATL M3P
6
FIREBIRD’S UNIQUE LMFP CAPABILITIES
LMFP KNOW HOW – STRATEGIC
COLLABORATION WITH CENTRAL SOUTHERN
UNIVERSITY (CSU)
THE CONCEPT
OUR PARTNER
BENEFITS OF PROCESS
Firebird will target a
substantial cost
advantage in LMFP
production by
bypassing the
manganese sulphate
crystallisation process.
CSU has strong
reputation for producing
world-leading battery
materials processes. CSU
staff include global
experts in the Li-ion
battery supply chain,
with alumni including the
founders of BYD and
Rongbay Technology
Will guarantee mix quality
This streamlined
approach not only
reduces costs but also
results in a higherquality LMFP product,
strengthening Firebird's
position in the market
Refer to ASX announcement dated 28/10/24 & 4/3/25
Less grinding = less cost
Largest cost of producing
MnSO4 is energy
consumed in
crystallisation process,
not crystallising is a huge
cost advantage
Further costs savings of no
packing, transport and
redissolving of MnSO4
Competitors who buy
MnSO4 as crystals and use
wet mix process will not
have same cost advantage
30 batches completed
100 batches expected to be
completed in total
All equipment ordered to
enable test work at one
Firebird R&D centre
Firebird intends to lodge
patents both within China and
internationally
8
FIREBIRD’S COMPETITIVE ADVANTAGE & POSITION IN
LMFP BATTERY VALUE CHAIN
RAW MATERIALS
L
M
PRECURSOR
INPUT MATERIALS
pCAM
LMFP BATTERY
LiCO3
Lithium
Manganese
LMFP CAM
Lithium Carbonate
Manganese Sulphate
Firebird’s competitive
advantage through patented
technologies and experience
MFP
(Fe Mn)PO4
F
Fe - Iron
Fe Salt
(inexpensive by product)
P
Phosphate
Phosphate Acid
(Fertiliser plants)
is created by mixing and
grinding Manganese, Iron
and Phosphate
Firebird’s competitive
advantage through solution
synthesis provides better
quality and lower cost
MFP
Created by mixing and
baking MFP, LiCO3 and
glucose.
CAM sold to cell maker and
turned into batteries
9
FIREBIRD LMFP BATTERIES
10
MANGANESE SULPHATE PLANT
AERIAL VIEW OF
PROPOSED PLANT
•
Preliminary design and key permits
secured in less than 12 months
•
Production Capacity – Battery grade 50kt
MnSO4 plus 10kt Mn3O4, (72.5Kt MnSO4
equivalent)
•
12.09 hectares land with 84,399sqm
building area
•
>5,000 sqm land available on site for
future expansion
•
Firebird can build the proposed plant in
12 to 15 months from making FID - a key
advantage of establishing operations in
China
•
Can be replicated worldwide
Note: Artist Impression
Refer ASX announcements 7/5/24, 2/10/24
12
SIMPLE & EFFECTIVE MANGANESE SULPHATE PROCESS
For full details refer to ASX announcement dated 7/5/24
•
Efficient and Cost-Effective
Operations: Firebird’s technical team has
developed a unique process
underpinned by a low capital intensity
design and lower operational costs,
demonstrating their expertise and
sector-leading credentials
•
Sustainable and Eco-Friendly: The
process is designed to be
environmentally sustainable, ensuring
that all residues are either consumed or
sold, minimising waste and
environmental impact
•
Innovative Proprietary Technology:
The project is supported by proprietary
technology specifically aimed at reducing
operational expenses (OPEX), enhancing
overall cost efficiency and
competitiveness
13
TIER-1 ECONOMICS & LOW-COST PATHWAY TO PRODUCTION
•
Economics: Feasibility Study completed in May 2024 outlined a compelling opportunity to
establish a near-term, cost-competitive, battery-grade manganese sulphate operation.
Key highlights included:
•
Low Capital Expenditure (CAPEX): US$83.5 million
•
Working Capital: US$10.7 million
•
Plant Capacity: Producing 50,000 tonnes per annum (t/a) of battery-grade MnSO4 and
10,000 t/a of Mn3O4, or an equivalent of 72,500 t/a of MnSO4
•
Sustainable Process: Facility designed to be environmentally friendly, generating no
wastewater and ensuring all residues are utilised by a cement plant
•
Operational Efficiency: Project OPEX very competitive with peers in China, profitable with
today’s pricing and does not depend on subsidies from joint venture partners or Government,
underscoring the plants economic viability
•
~60% of Financing Secured: Through indicative and non-binding agreements with key
partners, including China Chemical and China Construction Bank
•
Permits and Approvals:
•
All critical permits required to operate, including environmental, safety, and energy
obtained in a timely manner
•
Preliminary design completed and approved by the Jinshi High-Tech Industrial Park
Committee, covering roughly 80% of the requirements for the building permit
•
Building permit expected to be granted shortly after completion of the detailed
engineering design
Refer ASX announcements 7/5/24, 14/5/24, 28/5/24,10/9/24 and 24/9/24
CAPEX US$83.5M + Working Capital
US$10.7M
China
Equity
China Chemical CAPEX deferred
payment
Construction
Bank - CAPEX
China
Construction Bank
- Working Capital
14
FIREBIRD’S COMPETITIVE ADVANTAGE
MnSO4 & LMFP PROCESSES COMBINED DELIVERS
EXCEPTIONAL COST POSITION
$900
$800
$700
$600
FRB
FEASIBILITY
STUDY OPEX
US$579 /t for
Battery Grade
MnSO4
$500
$400
$300
~32% LOWER THAN FRB FEASIBILITY STUDY
OPEX
POTENTIALLY
~50% Lower
Than
Industry
Average
$200
$100
$-
BMI China Industry
Average
Using 44% Mn ore based at $5 / dmtu (MAY 2024)
Kiln and FRB
Process Savings
Removing Crystallisation,
Drying and Packing
Reduced Grinding
FRB Process with
Total Savings
INNOVATION & TECHNOLOGY
ADVANCED PROVEN TECHNICAL CAPABILITIES
•
Driven by the Company’s sector leading technical team, who bring decades of manganese and downstream processing experience, Firebird is
progressing technical development processing opportunities to continually innovate and improve operational efficiency, further driving
an already impressive low-cost base
•
Since establishing the team, HFBT has developed numerous processing opportunities led by the calcining kiln and 5 th generation
crystallisation reactor, and has established a strategic collaboration with China Southern University
•
The Company’s technology is advanced and commercially proven, setting Firebird apart from industry peers
•
Unique process prioritises cost efficiency, environmental responsibility, and quality
RESEARCH & DEVELOPMENT LAB
17
WORLD’S MOST ENERGY-EFFICIENT MANGANESE REDUCTION
ROASTING KILN
•
Innovative Technology for Reduced Energy Consumption:
Traditional Manganese calcining technology requires a minimum
of 300 kWh per tonne of feed, heating materials to 900°C and
then cooling with water and air, leading to significant energy loss
•
Revolutionary Energy-Saving Solution: Firebird’s proprietary
technology, currently under patent, recycles heat from the
calcined material to pre-heat incoming feed, drastically cutting
energy usage and boosting the cost-efficiency of its high-purity
manganese sulphate plant
•
Strategic Partnership with Sunward: Firebird entered a
development agreement with Zhongji Sunward Technology Co.,
Ltd, a prominent producer of rotary tunnel kilns in China.
Sunward will pay a 5% royalty on future sales revenue for using
this innovative technology
•
Numerous Industrial Applications: The energy-saving rotary kiln
technology is adaptable for various industrial uses
Pilot Plant Results
•
Following internal trials and independent reports from Sunward, the kiln demonstrated remarkable energy savings.
•
Compared to conventional kilns, which typically require more than 300 kWh per tonne of 44% Mn ore feed,
Firebird’s pilot kiln operates at only 80-100 kWh per tonne for 44% Mn ore feed
delivering 70% in energy savings
For full details refer to ASX announcement 18
dated 5/6/24, 12/9/24 and 21/10/24
DEVELOPING NEW 5TH GENERATION CONTINUOUS HIGHPRESSURE CRYSTALLIZATION REACTOR
1st generation
Single effect evaporator
(insert picture
here)
2nd generation
Multi-effect evaporator
3rd generation
MVR
4th generation
Single high pressure, high temperature reactor
Firebird’s 5th generation, patent technology,
utilising a continuous high-pressure system,
with 8% energy use of 1st generation
• 1/3 energy use of 4th generation
• Based on 4th generation system, it operates
continuously & residual energy is used in preheating feed solutions
CURRENT INDUSTRY
STANDARD:
Most companies are still utilising 1st to 4th generation
technologies for sulphate production
ADVANCED 5TH
GENERATION
TECHNOLOGY:
Firebird’s 5th generation technology is already in
successful commercial use, with three systems sold to
date
SIGNIFICANT STEAM
SAVINGS:
Steam is a major cost factor in sulphate production. This
advanced technology is expected to reduce steam
consumption to less than half of the industry average,
greatly improving cost efficiency
For full details refer to ASX announcement dated 7/5/24
19
OAKOVER MANGANESE PROJECT
OAKOVER PROJECT
KEY HIGHLIGHTS
• Long term strategic supply source
• Mining Lease Granted – Subject to Mining Proposal approval
PORT HEDLAND
• Oakover is a sizeable, low-cost project, near-surface, gently dipping geology
• Metallurgical test work demonstrated saleable 30 - 32% Mn concentrate
product achievable
• Hydrometallurgy test work demonstrated Battery Grade MnSO4 achievable
• Updated DMS Manganese Concentrate Scoping Study generated strong
results and highlighted Oakover as a long-life, high-quality operation:
NEWMAN
• 18-year Life of Mine,
•
1
WESTERN
AUSTRALIA
~A$741.3 M NPV at a discount rate of 8%
• Impressive IRR of 73.1%,
• CAPEX of A$123M
Mineral Resource
Classification
Tonnes (Mt)
Mn (%)
Fe (%)
SiO2 (%)
Al2O3 (%)
P (%)
Indicated
105.78
10.1
8.9
39.2
9.8
0.10
Inferred
70.87
9.6
8.0
36.5
9.5
0.09
Total
176.65
9.9
8.6
38.1
9.7
0.10
For full details refer to ASX announcements 10/3/22, 30/1/23, 23/3/23, 26/6/23 and 30/8/23
PERTH
21
INVESTMENT SUMMARY
Unique LMFP Capabilities in a Market moving towards Manganese
Cathodes
An Australian-owned company capable of producing LMFP , we specialise
in the processing and development of manganese battery cathode raw
materials
ASX:FRB
Share price as of 1 May 25
Shares on issue
$0.08
142.36 M
Market capitalisation
$11.4M
Options @ $1.00
12.0 M
Performance rights
2.2 M
Options @ $0.30
12.5 M
Options @ $0.40
12.5 M
Technology and Innovation
Firebird is committed to innovation. Our goal is to become a fully
integrated cathode manufacturer, delivering advanced solutions
worldwide
Cash on hand (30 March 2025)
$2.35 M
Low-Cost, Environmentally Friendly, Near Term
MnSO4 process is underpinned by a focus on low capital intensity
and operational costs, enabled by a plant that can be built in 12 to
15 months from FID
Canmax Technologies
9.7%
Tolga Kumova
9.5%
Sector-Leading Team
Firebird’s Chinese manganese battery chemicals team boasts more
than 50 years of manganese and chemical production experiences
Major Shareholders
Board (incl. related parties) & management
15.05%
Technology can be replicated anywhere
Firebird’s state-of-the-art research and proposed development facility in
China provides competitive advantage. However, can be replicated
worldwide
22
ASX:FRB
38 / 460 Stirling Highway
Peppermint Grove WA 6011
+61 (08) 6245 9818
www.firebirdmetals.com.au
23